Project Title:
Replacement of uPVC Pipes Transmission line (600LM)
Location:
From Post-1, Simulao to Diatagon Reservoir, Diatagon, Lianga, Surigao del Sur
POW Budget:
₱ 634,512.00 (CAPEX)
Date Constructed:
July 17, 2018
Date Completed:
August 6, 2018
Actual Project Cost:
₱ 598,468.00