The installation of Parallel Transmission/ Distribution Lines from Camangahan Collection Box to DENR Lianga was made possible thru the Capital Expenditure of Operation/ Technical Section for CY 2019. The Bidding for the procurement of Supply and Delivery of unplasticized Polyvinyl Chloride (uPVC) Pipes, Fittings, Materials and Appurtenances was awarded to Caraga Plumbing Concepts being the Single Calculated and Responsive Bidder on June 7, 2019 and the Notice to Proceed was issued on July 1, 2019, thereafter the excavation and laying of pipes started on August 2019. Based on the approved Program of Work, the project cost is Four Million Three Hundred Thirty Two Thousand Three Hundred Twenty Nine Pesos Only (₱4,323,329.00), but the Actual Cost based on the Certificate of Project Completion (duly completed on November 4, 2019) is Four Million One Hundred One Thousand Eight Hundred Twenty Two & 74/100 Pesos Only (₱4,101,822.74). The project will sustain the water needs at Zone 1, 7, 8, & 9 at Barangay Payasan, Baucawe, Anibongan, Liatimco, & Wakat especially the high elevation service connections. Normal condition of water flow will now be felt at Zone 1, 2 & 3 at Barangay Ban-as, Banahao, Poblacion, & Payasan respectively.